February 2016 Administrator’s Report

ADMINISTRATOR’S REPORT

February, 2016

SANITARY SEWER PROJECT:

Poggemeyer Design Group has submitted their contract for the sanitary sewer project.  The total cost is $88,600.00 broken down in the following manner:

Topographic Survey                                            $1,400

Design                                                                    36,000

Bidding                                                                     4,900

Construction staking                                              1,400

Engineering during Construction                        9,900

Construction Observation – … Continue reading

December 2015 Administrator’s Report

ADMINISTRATOR’S REPORT

DECEMBER, 2015

W. WOODCOX WATERLINE REPLACEMENT:

The waterline project is complete with the exception of two areas to be graded and re-seeded.  The final contract cost was $143,379.00, which included a change order of $554.00.   No additional funds are required from the village as the total award from … Continue reading

September 2015 Administrator’s Report

ADMINISTRATOR’S REPORT

September, 2015

 

W. WOODCOX WATERLINE REPLACEMENT:

Waterline replacement project is to start on 9/21/15, weather permitting.  The project is to be completed and closed out by December 31, 2015.

 

RENTAL WATER DEPOSIT NOT ENOUGH:

Renters that don’t own the home they are moving into must pay … Continue reading

August 2015 Administrator’s Report

ADMINISTRATOR’S REPORT

August, 2015

W. WOODCOX WATERLINE REPLACEMENT:

The pre-construction meeting was held on August 6, 2015 with Hohenbrink Excavating, Poggemeyer Design Group, Jeremy Kosch, water operator and myself to review work schedules, any anticipated problems during excavation for the new waterline, etc.  It is anticipated work would begin end … Continue reading