December 2015 Administrator’s Report

ADMINISTRATOR’S REPORT

DECEMBER, 2015

W. WOODCOX WATERLINE REPLACEMENT:

The waterline project is complete with the exception of two areas to be graded and re-seeded.  The final contract cost was $143,379.00, which included a change order of $554.00.   No additional funds are required from the village as the total award from … Continue reading

September 2015 Administrator’s Report

ADMINISTRATOR’S REPORT

September, 2015

 

W. WOODCOX WATERLINE REPLACEMENT:

Waterline replacement project is to start on 9/21/15, weather permitting.  The project is to be completed and closed out by December 31, 2015.

 

RENTAL WATER DEPOSIT NOT ENOUGH:

Renters that don’t own the home they are moving into must pay … Continue reading

August 2015 Administrator’s Report

ADMINISTRATOR’S REPORT

August, 2015

W. WOODCOX WATERLINE REPLACEMENT:

The pre-construction meeting was held on August 6, 2015 with Hohenbrink Excavating, Poggemeyer Design Group, Jeremy Kosch, water operator and myself to review work schedules, any anticipated problems during excavation for the new waterline, etc.  It is anticipated work would begin end … Continue reading

July 2015 Administrator’s Report

ADMINISTRATOR’S REPORT

July, 2015

W. WOODCOX WATERLINE REPLACEMENT:

The W. Woodcox waterline bid was opened on Wednesday, July 15, 2015.  The Village received 2 bids.  All Purpose Contracting, Inc. of Delphos submitted a bid of $142,995.00 and Hohenbrink Excavating, LLC of Ottawa submitted a bid of $142,825.00.  Both bids were … Continue reading