We have received an updated calendar from the contracted ODOT crew on the SR 49 Project. The following schedule is subject to change:
• Tuesday (9/2): Milling (Day 1)
• Wednesday (9/3): Milling (Day 2)
• Thursday (9/4): Milling (Day 3)
• Friday (9/5): “Will try to complete milling in 3 days but may
need Friday to finish”
• Monday (9/8): Mainline Paving (Day 1)
• Tuesday (9/9): Mainline Paving (Day 2)
• Wednesday (9/10): Mainline Paving (Day 3)
• Thursday (9/11): Mainline Paving (Day 4)
• Friday (9/12): Paving Intersections (Day 5)
DURING THIS TIME 7:00 AM-5:00 PM THERE IS NO PARKING ALLOWED ON THE STREETS WITHIN VILLAGE LIMITS.
Thank you for your cooperation.